PIKE COUNTY
WEEK OF MAY 26, 2024
CHILLICOTHE - The following construction projects are anticipated to affect highways in Pike County next week. All outlined work is weather permitting. Projects with active or future traffic impacts are linked to OHGO.com
NEW
State Route 772 Culvert Replacement
Work is set to begin June 10 for a culvert replacement project between S.R. 220 and Strickland Road. Work will occur daily for this construction. S.R. 772 will be closed for the duration of the project; traffic will be detoured via S.R. 124 to Water Street to Main Street to S.R. 41 to U.S. 50 to South Paint Street.
Estimated completion: June 14 by 3:30 PM
County Road 8 Bridge Replacement
Work has begun as of May 8 for a bridge replacement project on C.R. 8 (Dry Bone Road) between S.R. 41 and Fairview Road. Work will occur daily for this construction. Dry Bone Road will be closed for the duration of the project; traffic will be detoured via Fairview Road to Lapperell Road to S.R. 41.
Estimated completion: Summer 2024
State Route 220 Resurfacing
Work has begun as of May 6 for a resurfacing project on S.R. 220 between Zahns Corner Road and East Emmitt Avenue. Work will occur daily for this construction, at least one lane will be maintain using flaggers.
Estimated completion: Summer 2024
State Route 32 Resurfacing
Work has begun as of May 6 for a resurfacing project on S.R. 32 between the Adams County line and Goff Road and between Beaver Creek Road and Tennyson Road. At least on lane will be maintained for the duration of the project. Estimated completion: Summer 2024
Super Load
A Super Load is expected to impact various roadways in Pike County. To sign up for route information and updates, visit transportation.ohio.gov/superload
ONGOING:
State Route 772 Slide Repair
Work has begun as of March 11 for a landslide repair project on S.R. 772 between McKinney Road and S.R. 124. Work will occur daily. One lane of traffic will be maintained using temporary signals for the duration of the project. Estimated completion: Fall 2024
State Route 104 Bridge Replacement
Work has begun as of February 26 for a bridge replacement project on S.R. 104 between S.R. 32 and Long Fork Road. S.R. 104 will remain open until June 1.
Starting June 1, S.R 104 will be closed all directions for approximately 2 weeks.
Traffic will be detoured via S.R. 32 to U.S. 23 to S.R. 348.
Following the 2-week closure, the Southbound lane of S.R. 104 will be open from S.R. 32. Estimated completion: Fall 2024
County Road 50 Slide Repair
Work has begun as of February 12 for a landslide repair project on C.R. 50 (Watson Road) between Mutton Run Road and Hay Hollow Road. Work will occur daily from 7 AM to 5 PM. The road will be closed for the duration of the project, North Bound traffic will be detoured via S.R. 335 to Higby Road to Old S.R. 35. South Bound traffic will be detoured via Old S.R. 35 to Higby Road to S.R. 335. Estimated completion: Summer 2024.
For more information contact: District 9 Public Information Office at 740-774-8834.