Charleswood School project continues ahead of schedule
During a brief meeting of the Elementary School Building Committee on Tuesday, members got updates on work progress, the budget, the schedule and next steps. Chris Kenney, project manager at Vertex, reported the $158 million project remains ahead of schedule, with substantial completion expected on July 1, 2027, and final completion/ready for students by Aug. 27, 2027. (The contract has that date as Jan. 3, 2028).
Uprise RI
Recap: Lincoln Panel Backs Splash Pad Design, Street Paving Survey
Lincoln's purchasing panel sent the Town Council recommendations to fund design of a grant-backed splash pad at Manville Park, with construction bids targeted for spring, and a new road condition study meant to update the town's paving priorities. It also backed drainage design for a flooding problem near Lower River Road and a new, cheaper town calendar printer.