Charleswood School project continues ahead of schedule
By Susan Gonsalves,
4 days agoDuring a brief meeting of the Elementary School Building Committee on Tuesday, members got updates on work progress, the budget, the schedule and next steps. Chris Kenney, project manager at Vertex, reported the $158 million project remains ahead of schedule, with substantial completion expected on July 1, 2027, and final completion/ready for students by Aug. 27, 2027. (The contract has that date as Jan. 3, 2028).