NCDOT outlines progress on Polk County road projects
By Storme Smith,
2026-09-29Officials share timeline of US 176 repairs, cite funding as main issue with Howard Gap Rd.
COLUMBUS—NCDOT officials updated Polk County residents Monday on the status of major road projects, including work on U.S. 176, Green River Cove Road and Howard Gap Road.
The meeting, held at the Womack Building in Columbus, brought NCDOT engineers and local officials together with residents for updates and questions about road closures, construction schedules, emergency access and funding.
Wesley T. Grindstaff, division engineer for NCDOT Division 14, opened the meeting by introducing staff members working on projects throughout the region. District Engineer Troy Wilson and other NCDOT engineers then provided updates before taking questions from residents.
Several Helene-related projects are moving forward across the county. Polk Bridge 29 near the school is entering its final phase of completion, while work on the Lake Adger bridge continues. Construction has also begun on U.S. 176, the Edney Road project is about 9% complete, and repairs to the bridge on Pearson Falls Road are expected to begin soon.
Green River Cove Road was a major focus of the meeting, with NCDOT officials outlining extensive repairs along the route.
Contractors have begun replacing damaged pipes, repairing bridges, and stabilizing sections where portions of the travel lane were lost. The switchback section presents additional challenges because of steep terrain and limited space for construction equipment.
Officials said retaining walls will be required, including one section approximately 1,700 feet long. The work will involve heavy equipment and drilling, and portions of Green River Cove Road will eventually require a hard closure while crews construct the walls.
Residents also raised concerns about the effect of closures on businesses, camps and visitors. NCDOT representatives said they are working with contractors to schedule bridge closures in a way that limits impacts on businesses and will provide additional information as construction schedules are finalized.
U.S. 176 between Saluda and Tryon also generated extensive discussion as the project moves into construction.
Work has begun on the upper section of the road. NCDOT officials said that portion could potentially return to normal traffic within about a year, while the more heavily damaged section through the gorge will take considerably longer.
Representatives of the U.S. 176 contractor said the project presents significant challenges because of the extent of the storm damage and the importance of restoring the connection between Saluda and Tryon for residents and businesses.
Safety will remain a primary concern during construction, officials said. Motorists, cyclists and pedestrians were urged to obey temporary traffic signals, barricades and other work-zone controls. Officials also cautioned that some sections of roadway may appear passable while underlying portions remain unstable.
NCDOT officials said the historic bridges along U.S. 176 are expected to remain in their current configuration.
Residents questioned delays, traffic control and emergency access, as well as why some work has not been visible. NCDOT representatives said engineering, drainage, environmental reviews and other preparations often must be completed before major construction can begin.
Howard Gap Road drew some of the meeting’s most extensive discussion.
NCDOT officials said funding remains the primary obstacle to reopening the road. The department had previously prepared an application for a federal PROTECT grant, but that funding opportunity was withdrawn. A new opportunity has opened, and NCDOT plans to submit an application in October.
Preliminary engineering for Howard Gap Road has already been funded and completed, including geotechnical drilling. NCDOT has refined the estimated project cost to approximately $12 million.
Because the damage to Howard Gap Road was not associated with a federally declared disaster like some other storm damage, NCDOT said the state would face significant costs without federal assistance.
Residents also asked whether Howard Gap Road could accommodate increased truck traffic if it is reopened, particularly during Interstate 26 closures.
NCDOT officials said the department can impose restrictions on secondary roads when structural or pavement limitations support them. Broader restrictions, however, require legislative consideration.
If funding becomes available, officials said NCDOT would be prepared to move forward with Howard Gap Road, although construction could take about two years because of the extent of the work required.
The county and NCDOT also discussed improving communication about road closures and construction progress.
Officials said updated information, recordings, and presentations will be posted through the county’s NCDOT projects webpage. An inquiry form will also be available for residents to report concerns directly to transportation officials.
NCDOT officials encouraged residents to report work-zone concerns directly to the department rather than relying on social media posts.
The meeting gave residents and transportation officials a chance to discuss the numerous road projects underway across Polk County and address questions about the work still ahead.