Gateway Development Commission launches second Hudson Tunnel Project boring machine

By Liz Carey,

15 hours ago
https://img.particlenews.com/image.php?url=4dfwTH_1HNpgWit00

The Gateway Development Commission announced a second tunnel boring machine has started mining the Hudson Tunnel Project’s southern tube.

Mining on the southern tunnel tube began in November, after the northern tube tunneling began in October. The two machines are building the first 5,100 feet of the new rail tunnel tubes in New Jersey from the tunnel portal in North Bergen to the Hudson County Access Shaft on the border of Weehawken and Hoboken. When they read the access shaft, the tunnel boring machines will be removed and replaced with a second set of machines designed to bore through the mixed ground conditions under the Hudson River. Officials estimate building this section of the tunnel tubes will take an estimated one year.

The tunnel boring machines are designed to excavate and install the tunnel lining at the same time. Each machine will install nearly 850 rings of the tunnel lining. To date, the northern tunnel machine has bored an estimated 400 feet, and installed more than 60 tunnel lining rings.

“The Hudson Tunnel Project is moving forward full steam ahead – we’ve now launched two tunnel boring machines, one for each of the new tunnel’s tubes,” Alicia Glen, New York GDC Commissioner and Co-Chair, Balpreet Grewal-Virk, New Jersey GDC Commissioner and Co-Chair, and Tony Coscia, GDC Amtrak Commissioner and Vice Chair. “Every foot that these machines bore brings us closer to delivering the modern, reliable rail system our region needs.”

The machines currently in use are single shield machines designed to cut through hard, dry rock. Each machine has a 28-foot, 8-inch diameter cutterhead and trailing gantries the extend roughly 500 feet and weigh more than 1,680 tons.

“The start of tunnel boring last month was a major milestone for the Hudson Tunnel Project, but it was only the beginning,” GDC Chief Executive Officer Tom Prendergast said. “Launching the second tunnel boring machine marks another significant step toward delivering the most urgent passenger rail infrastructure project in America. We are proud of the hard work that got us to this milestone and committed to bringing the same dedication and grit to the job every day until it is done.”

The post Gateway Development Commission launches second Hudson Tunnel Project boring machine appeared first on Transportation Today.