Denver RTD begins work to extend commuter rail N Line
By David Lassen,
12 hours agoDENVER — The Regional Transportation District this week launched development activities for the N Line commuter rail extension, which would add 5.5 miles to the route north of Denver.
The RTD board has approved $12 million for development work for the extension, which would add two stations in Thornton north of the current terminus at Eastlake/124th Street. That funding will address the environmental review, preliminary engineering, and other technical work to update previous planning efforts, preparing the project to pursue state and federal funding. Adams County will also contribute to the effort.
“Completing the N Line is about connecting people to opportunity and strengthening the communities that make Adams County and the north metro region such vibrant places to live and work,” Julie Duran Mullica, chair of the Adams County board of commissioners, said in a press release. “Through this partnership, we’re bringing local governments, community leaders, and residents together around a shared vision for the future. The N Line extension will help improve access to jobs, education, services, and economic opportunity while supporting the continued growth of our region.”
In starting the development process, the RTD has created a project management team and begun coordination activities with Adams County and other parties.
“The board is committed to doing the work necessary to advance the N Line extension in a thoughtful and responsible way,” said RTD Board Chair Patrick O’Keefe. “This investment allows us to develop a clearer understanding of the project’s scope, costs, schedule, and funding opportunities while strengthening the partnerships that will be essential to moving the project forward. Adams County has been an incredible partner as we have collectively kick-started this project from dormancy to an urgent delivery plan.”
The extension will follow a former Union Pacific rail line, but project manager Nabil Haddad told KMGH-TV that many of the details will be determined during the development phase.
“Does the infrastructure allow for having double track or one track? How much is the headway between trains?” Haddad said. “… We do not have that information yet, because what worked 15 years ago [when the route was first planned] obviously does not work right now.” More details should be available by August 2027, he said, with construction to begin no earlier than 2029.
A 2025 report estimated the capital cost of the extension at $395.7 million, with annual operating costs of $5.4 million.
The N Line is currently a 13-mile, seven-station route running north from Denver Union Station, with stops in Commerce City, Northglenn, and Thornton. In 2021, its first full year of operation, it carried about 760,000 riders; in 2025, ridership was more than 1.2 million, the RTD says.