undefined
Posts
undefined
Followers
Coos Bay Rail Line slowed by bridge issue
By David Lassen,
2026-09-19COOS BAY, Ore. — The Coos Bay Rail Line, which connects the International Port of Coos Bay to Union Pacific, continues to operate at reduced speed while awaiting materials to complete repairs on a bridge that recently shut down the line for a week.
Jefferson Public Radio reports that a train crew noticed problems with the bridge at Cushman, Ore., and an inspection found pieces of the wooden structure — two timber caps, three posts, and a mudsill — had deteriorated to the point of failure.
The Port’s CEO declared an emergency that day, allowing the award of a no-bid contract for repairs. That contract, for $155,866, went to Scott Partney Construction. Completion of repairs is dependent on new posts and a mudsill being cut, milled, and treated; those parts are not expected until October.
Port commissioners later ratified the decision to award the contract at a Sept. 17 meeting. Brian Early, general manager of the rail line, told the commissioners the bridge is one of many with aging timbers: “These are bad, and in all honesty and candor, you’ve got a lot of those out there,” Early said, according to the broadcaster. “We’ve got a list.”
The 134-mile rail line to the connection with UP at Eugene, Ore., is a crucial element of the port’s plan to build a new container terminal. The Pacific Coast Intermodal Port would build a facility capable of handling 2 million TEUs (20-foot equivalent units, the standard measure of international containers), and would move all its container traffic by rail. The projected $2.3 billion project has received a series of federal grants as well as funding from the Oregon legislature [see “Port of Coos Bay board approves …,” Trains.com, June 23, 2026].
— To report news or errors, contact trainsnewswire@firecrown.com.