State seeks comments on plan for busy intersection
By Drew C. Wilson,
2026-08-19The North Carolina Department of Transportation is seeking comments on proposed intersection improvements on Nash Street (N.C. 58) where it meets Airport Boulevard and Lake Wilson Road.
NCDOT officials say the changes are needed to improve safety and mobility for motorists, bicyclists and pedestrians.
The total cost of the project is $13.62 million, with $5.52 million for property acquisition and utilities and $8.1 million for construction costs.
The project timeline calls for right-of-way acquisition in the fall of 2027 and project bid letting by the fall of 2030.
According to a project overview, the work “will improve the intersection by adding turn lanes and bicycle and pedestrian accommodations.
The DOT project, called U-6111, is being planned in coordination with the city of Wilson.
To see more details of the project including maps of the proposed improvements or to make comment, go to https://publicinput.com/nash-airport-lakewilson .
State officials say the improvements will reduce congestion, improve safety and support future growth.
Andrew Barksdale, a NCDOT spokesman, said there will be no open house for comments on this project.
“The city of Wilson has endorsed it and has been briefed several times about it from NCDOT Division 4 staff in Wilson,” Barksdale said. “The public comment period ends Aug. 28.”
When the Times first reported this project in 2024, the cost of right-of-way acquisition was estimated at $700,000 with $6.5 million for construction. That estimate has more than doubled, according to Barksdale, with some features added.
“This is due to better scoping and more accurate estimates as the project, which is mostly the same as in 2024, was fine-tuned,” he said. “Not counted in the 2024 cost estimates were some sidewalk and multi-use path (aka, paved greenway) included in the project. But, mainly we now have a better idea of the true cost — $13 million, or double what we estimated in 2024.
In the 2024 story about this project, a Times story reported that according to average annual daily traffic data gathered by the NCDOT, in 2023, eastbound traffic at this intersection on Airport Road was 10,600 vehicles daily and is forecast to be 13,300 by the year 2050. Each day in 2023, approximately 23,700 vehicles headed north on N.C. 58, and that number is forecast to increase to 27,100 by the year 2050.
The same data shows that in 2023, approximately 18,200 vehicles turned onto or off of Airport Road onto N.C. 58 daily, and that number is forecast to increase to 23,200 by the year 2050.