undefined
Posts
undefined
Followers
Foot path going in for Newberg-Dundee Bypass Trail
By Gary Allen,
15 hours agoThe Newberg-Dundee bypass trail is another step closer to fruition.
Salem contractor Emery & Sons Construction Group began Nov. 20 pouring the concrete foot path on a 670-foot foot bridge that will span the Hess Creek floodplain adjacent to the northeastern end of the Newberg-Dundee bypass.
It represents the first of two lengthy bridges on the project to construct the Newberg-Dundee Bypass Trail; the second will cross the Chehalem Creek drainage.
In August, the Salem-based company installed massive steel girders designed to support the nearly mile-and-a-half path for pedestrians and cyclists to travel unencumbered between the bypass at Highway 219 on the east to Rogers Landing in the west in the first phase of the project. Future phases will see the path continue on to Eighth Street in Dundee.
The trail is a Chehalem Park and Recreation District project that is a component of the larger Chehalem Heritage Trails system.
The Initial $1.82 million in funding for the project came in 2021 from the Oregon Transportation Commission through a state Oregon Community Paths grant, a function of the Oregon Department of Transportation. The park district, city of Newberg and other local partners provided a $780,000 match in order to secure the grant.
Phase 1 of the project is projected to cost $2.6 million and Phase II is expected to come in at $3.8 million for an overall cost of $6.4 million.
Park district officials predicted the first phase of the project will be completed by year’s end.