Public blocked from using two-thirds of popular Broad River pier. What's going on?
By Karl Puckett,
6 days agoThe public’s been blocked from reaching two-thirds of an iconic fishing pier on the Broad River in Beaufort.
What’s going on?
A recent inspection showed that the massive beams supporting the 67-year-old pier, which is part of the old bridge across the river, are deteriorating, said Jared Fralix, the county’s assistant county administrator for infrastructure.
As a result, the section was closed Friday for public safety reasons, Fralix said. The problematic support beams are located under the farthest reaches of the pier in deeper water.
The full pier stretches 1,800 feet from shore, providing fantastic views of the beautiful Broad, which spans nearly 2 miles at this location.
It’s also a popular place for inshore fishing, providing access to deeper-water fish such as cobia and blacktip sharks as well as red drum, black drum, spotted seatrout, sheepshead, southern flounder and whiting.
With the barricades in place, only 600 feet, or third of the pier, remains accessible. The remaining two thirds, or the outermost reaches of the pier, is closed permanently.
The iconic pier sits in the shadow of the current Highway 170 bridge, built in 2004 as the new divide between northern and southern Beaufort County.
Change was coming for the pier no matter what.
Earlier this year, the county announced plans to demolish the pier and replace it with a new one that’s about 600 feet. That’s about same distance as the newly restricted pier the county is now contemplating.
But the loss of the full length of 1,800-foot-long pier is coming sooner than expected.
Closing of the outermost section came at the recommendation of the county’s consulting engineers, Fralix said. The county is now getting quotes for putting up a permanent fence, he said.
The fishing pier is the old Highway 170 crossing the Broad River built in 1959 and rehabilitated in 1973. It was converted into a fishing pier in 2004 when the new bridge opened.
Demolishing the old pier
The county is working on a plan to demolish the current pier, which will cost about $3 million, Fralix said. It can’t be partially demolished because that could damage the remaining section, he said.
A plan to demolish the fishing pier is expected to be ready by 2028, Fralix said.
New pier in the works
At the same time, the county is working on a design for new pier. It is 60% done. The cost of the new pier will be $15-$20 million, but it’s not a done deal.
“That will have to be considered with other capital needs the county has whether the project moves forward, or in an alternate way,” Fralix said.
The county is considering partnering with the private sector because of the high cost. A private party most likely will be interested in a marina, charging for access or building a restaurant, but “we may be surprised” at what is proposed, Fralix said.
He predicted it would take three to four years to fund, permit and build a new pier.
Brian Bauer, the head of the Beaufort County Engineering Department, said a 600-foot-long fishing pier would get anglers near deep water and good fishing. Many people who use the pier now, he noted, don’t go out past 600 feet.
The county plans to move forward with the demolition whether a new pier gets built or not, Fralix said.