WL Board of Works approves confidentiality agreement

By LARRY FESTA Staff Reporter,

4 days ago

A newly signed information management agreement between SK hynix, the City of West Lafayette, and Bureau Veritas will aim to maintain confidentiality for the $4 billion dollar semiconductor plant project. Bureau Veritas will provide inspection services to the project.

The West Lafayette Board of Public Works and Safety convened Tuesday morning to approve agreements for the involvement of a new third party, Bureau Veritas North America, in the ongoing semiconductor plant project being developed by South Korean multinational firm SK hynix.

Bureau Veritas North America is a major building inspecting and testing firm operating in the United States and Canada. Redevelopment Commission Attorney Eric Burns said that the company’s inspection work on the facility will be necessary for the project to succeed.

“We need the best expertise in the world to make sure that everything is being done correctly,” Burns said. “Bureau Veritas is that organization.”

As part of Bureau Veritas’ involvement, the board approved a new communication and information management agreement. Burns said that the agreement is intended to secure confidentiality for the project.

“It makes sure that the confidential information that (SK hynix) has about its plant and its operations is protected, even though we now have a third party involved,” Burns said.

The board also approved the agreement for Bureau Veritas’ involvement in inspection of the new facility and the fee proposal for the inspection plan. The inspection plan fee will be paid in full by SK hynix and not West Lafayette

New road closures are also taking effect in West Lafayette.

Pathfinder Drive will be closed between Dawn Avenue and Provenance Boulevard from 9 a.m. on Nov. 17 through Nov. 20 to facilitate the implementation of a new stormwater drain.

A lane shift will also occur on Yeager Road from 9 a.m. on Nov. 17. The closure was requested by GroundBreakers LLC so that the company could drill 35 test holes along the road to locate existing underground utilities for future engineering design work. The project is estimated to take 10 days.

The West Lafayette Board of Works will reconvene after Thanksgiving.