COVINGTON — Plans have been filed for a 1.4 million-square-foot data center proposed to be constructed on Gregory Road in Newton County.

The project was submitted March 27 for a Development of Regional Impact review by the Georgia Department of Community Affairs.

According to the DRI filing, the project encompasses about 520 acres in unincorporated Newton County. The project includes a data center campus on 213 acres, with the remaining 307 acres earmarked for 27 residential lots. Gregory Road runs from Alcovy Road to Flat Rock Road, just south of Lake Varner.

The property is owned by JBW Investments LLC and JF Land Investments LLC, with John B. Williams and Universal Planning and Development listed as the developers.

Project plans call for development in three phases, with overall completion set for 2036. The estimated value of the project at buildout is $5.7 billion, with annual tax revenues at an estimated $19 million.

While the property is located in unincorporated Newton County, the DRI filing indicates that the developers intend to seek annexation into the city of Covington and rezoning of the property.

Water demand for operation of the data center is estimated at 1 million gallons per day. The DRI filing shows that the city of Covington does not have sufficient wastewater treatment capacity to meet the expected demand of 360,000 gallons per day. According to the filing, the developer is proposing to construct on on-site water treatment facility to handle the release of water from the cooling towers in the data center buildings. Alternatively, the developer could pursue a connection to the Eastside Sewer Main.

The traffic impact from the data center is estimated at 494 trips per day. The developer is proposing to abandon a portion of Gregory Road to accommodate the new development, which will result in a dead-end road at the southeast end of Gregory Road and disconnection of a connecting roadway. As a consequence, local traffic would be redirected to use the intersection of Alcovy Road and Ga. Highway 142.

This proposed data center is in addition to another one that JBW Investments and Universal Planning and Development have in the works at 375 Flat Rock Road. The developers received a rezoning last June in Newton County for 15.56 acres of a 430-acre site. Only the 15.5 acres of the total tract lie in unincorporated Newton County, with the remainder in Covington. A condition of the rezoning from Agricultural to Heavy Industrial was a requirement that the property use be limited to a data center. The property in the city limits was already zoned Heavy Industrial.

Owners of the Flat Rock Road property had previously sought to develop a mixed-use project on the site, including multiple forms of residential uses along with industrial.

Developments of Regional Impact are large-scale developments that are likely to have regional effects beyond the local government jurisdiction in which they are located. The projects are reviewed by the Georgia Department of Community Affairs, but the host government maintains the authority to make the final decision on whether a proposed development will or will not go forward.

emoji_like
1

Comments