County OKs additional expenditures for Hwy. 212 work
By Al Lohman,
7 hours agoPhase one of Highway 212 improvements between Carver and Cologne were completed in October 2024, but conversations about subsequent repairs and project cost overruns have continued since then.
This past spring, the county board approved a change order for nearly $3.8 million for a permanent repair to a settled section of roadway on eastbound Highway 212 in Dahlgren Township just west of Highway 43 caused by unstable soil conditions. Last Tuesday, Oct. 3, the board authorized the Carver County engineer to approve additional expenditures — up to $7.5 million — associated with additional change orders and cost overruns.
The authorization will cover repairs to additional pavement settlement that has occurred at several other culvert crossings, project engineers explained at the meeting. Plus, cost overruns for additional work and quantities of materials required to make those repairs, such as additional muck excavation and sand and aggregate materials.
A separate amendment to the cooperative agreement between Carver County and the Minnesota Department of Transportation to advance the Highway 212 project was executed earlier to allocate $3.2 million of additional MnDOT funding toward the dip repair. The county portion of the project, projected now to be at $3.8 million will be paid for from the county transportation sales tax in the road and bridge budget.
The repairs are expected to be completed by late November. Highway 212 project leaders Indicated that once the repairs are made, MnDOT will accept the final project and have future responsibility for the roadway.
Other transit news
In response to safety concerns, the county board also took action at its Nov. 3 meeting on another section of county roadway: the intersection of county highways 11 and 44, or Jonathan Carver Parkway and Big Woods Boulevard near Carver.
That intersection has been the site of 27 crashes in the past 10 years — three injury crashes and one fatal just in the past year, according to county engineers.
A roundabout project has been proposed for 2028, since accelerated to 2027, but in the interim given continued concerns and growing traffic volumes, public works engineers have been exploring interim solutions that were explained at the meeting.
The preferred alternative was a compact, or mini roundabout, with a smaller footprint, slightly raised center island and striping guidance for motorists. But timing, weather and lack of construction bidders had county engineers proposing the all-way stop interim alternative for now.
County law enforcement is expected to provide additional patrols in the area as motorists get used to the new traffic control.