Utility commission green lights Buck Station expansion
By Janet Briggs,
1 days agoROWAN COUNTY — The Buck Station expansion got its stamp of approval from the North Carolina Utilities Commission on Tuesday, moving the 850 MW expansion forward. However, it comes alongside a statewide rate increase.
On Nov. 17, the North Carolina Utilities Commission (NCUC) issued its certificate of public convenience and necessity for the proposed construction of two 425 MW capacity natural gas turbines (CTs) at Buck Station. The finding comes after an over year-long process between Duke Energy and NCUC, which drew some Rowan County public pushback in March 2026.
According to Duke Energy spokesperson Bill Norton, the ruling is a “significant step forward.” Duke Energy will still need approval for an air permit before construction on the expansion begins, but it still anticipates the online date of 2030 is a reasonable goal.
The decision comes along with approval of the 2026 Carbon Plan and Integrated Resource Plan (CPIRP), which encompasses various energy production markets, load goals and environmental recovery under Duke Energy’s purview.
As part of that approval, Duke Energy residential rates statewide will increase 3.7 percent over the next two years. The Buck Station expansion project is only one of the projects and demands contributing to the rate increase. Duke Energy’s North Carolina President Kendal Bowman commented on the rate increase and overall plan approval in a statement from Duke Energy.
“We know families and businesses are watching their energy bills closely, and we take that seriously,” Bowman said. “The plan reflects an all-of-the-above approach — natural gas, solar, batteries and new nuclear — shaped by our customers and many partners across the state. We appreciate the commission’s careful review, and we’re committed to working together to keep the lights on, support economic development and hold down costs as the Carolinas grow.”
In October, public staff recommended approval of the expansion with certain guidelines attached, but the NCUC did not include any of the recommendations in the final ruling.
The public staff-recommended guidelines included quarterly construction progress reports from Duke Energy, which would require notification of missed milestones by more than 90 days or cost increases over 10 percent. They also recommended a spending cap for cost recovery of $1.452 billion for the project.
Additionally, the public staff recommended that Duke Energy report any termination of large-load electric service agreements over 1,000 MW within six months to justify that the Buck Station development was still necessary.
In its final approval, the NCUC addressed not taking the 1,000 MW large-load customer termination reporting, arguing it shows only part of the picture for grid considerations.
“Additions, amendments or terminations in isolation only paint one part of the boarder picture. For example, 1,000 MW of terminations would have little impact on the overall status of the pipeline if 1,000 MW of new load enters the pipeline or if remaining customers increase their service requests by 1,000 MW,” NCUC wrote.
They argue that other restrictions passed in the CPIRP and other existing avenues would account for large load contract changes and their impact on the need for the Buck Station expansion.
Earlier released timelines estimated that construction would begin in roughly 2028, barring delays with final air permits.