Raleigh's got draft rules for data centers. Here's how you can see and comment on them.

By Nolan Wilkinson,

5 days ago
https://img.particlenews.com/image.php?url=43pB3h_1H8zOqkz00
Andrew Wray, senior engineer for high performance computing, checks the level of heat produced from a data center that is cooled from below a raised platform on Tuesday, January 28, 2025 in Morrisville, N.C. Robert Willett/rwillett@newsobserver.com

Raleigh has released its draft data center rules and is asking the public for input.

The proposed ordinance, released Monday, more specifically defines what constitutes a data center and list new requirements for data centers over a certain size.

The Raleigh City Council enacted a six-month data center moratorium in October lasting until April 2027 to give the city time to finish the ordinance and get public input.

What does the ordinance do?

  • Defines data centers in the city code and distinguishes between minor data centers under 10,000 square feet and major ones that are bigger than that
  • Gives performance and design standards for noise, vibration, lighting, buffers and generator impact
  • Requires environmental and infrastructure review assessments for water capacity, stormwater impact, potentially hazardous materials, energy demands, noise and vibration
  • Regulates how data centers are decommissioned and what must happen if they are abandoned.

How to give input

The city Planning Commission will host a meeting to talk about the proposed ordinance Dec. 8 at a location to be determined.

The public can comments on the proposal at engage.raleighnc.gov/f26221