undefined
Posts
undefined
Followers
Bellefonte waterfront hotel to open as Hilton Tapestry property
By NCPA Staff,
3 days agoBellefonte, Pa. — The hotel planned for Bellefonte’s waterfront will be a 92-room, six-story property in Hilton’s Tapestry brand, its developer told Borough Council on Monday, Nov. 16.
“This is going to be a Hilton flag product,” said Edward Tubbs, a partner and CEO of State College-based Hospitality Asset Management. He described Tapestry as a boutique brand.
Tubbs said crews are trying to finish the deep foundation and groundwork before winter shuts down work. Vertical construction could start “probably mid-March, beginning of April,” he said, and the hotel would open in “somewhere around that 18 to 24 month range” if all goes well.
He said the rooms would be about 30 kings and 60 queens. Some second-floor rooms will have Juliet balconies looking down on Spring Creek, and there will be a bridal suite, a restaurant and event space for “just shy of 100” people, he said. The name will nod to the area’s iron history, he said.
The presentation was information only, and council took no action on it.
In its business meeting, council conditionally approved adding a second, optional health insurance plan for borough employees through the Pennsylvania Municipal Health Insurance Cooperative. According to the agenda, the plan has a $750 or $1,500 deductible, offset by a borough contribution of $500 or $1,000 to a health reimbursement arrangement. It does not apply to retirees, and approval depends on agreement from the borough’s two unions, police and AFSCME, the agenda said. The plan passed on a roll-call vote, and every member heard answering the roll said yes.
Council also authorized a letter supporting the Bellefonte Borough Authority’s state Local Share Account grant application to replace the ultraviolet treatment system at the wastewater treatment plant. The project is estimated at $615,000 and requires no local match.
Council also awarded a $32,750 contract to Hoffman Leakey Architects to design accessibility upgrades at the Bellefonte train station, including a ramp, a push-button door and restroom changes, paid for with Community Development Block Grant money, according to the agenda. It also approved an amendment to the land development plan for the stage at Talleyrand Park.
The borough manager said PennDOT has recommended barring left turns from Phoenix Avenue onto Water Street from 7 to 9 a.m. and 4 to 6 p.m. Borough staff have concerns about how well that would work as the Benner Pike corridor grows, and PennDOT will take another look, the manager said. Council took no action.
In a budget work session, council reviewed a proposed 2027 capital projects fund of $3,255,020. The largest item is about $1.3 million to rehabilitate the Corning water tank, according to the agenda. The budget returns to council Monday, Dec. 7.