Bly Road completion set for December as Independence data center construction continues
1 days ago
KANSAS CITY, Mo. -- Bly Road, the only road leading in and out of the neighborhood next to the incoming Nebius data center, remains unfinished more than seven months later. In April, when the south end of Bly Road closed, residents were told the road would be finished in three-to-six months, no later than fall. After backlash from residents concerned about the unfinished road during the winter months, NorthPoint Development, the company responsible for finishing the road, said it would allocate additional resources to get the road finished by November.