Drainage board OKs Microsoft site dewatering
By WVPE 88.1 Elkhart/South Bend,
1 days agoPeople who live along Juday Creek are concerned about the first plans to temporarily drain land near the Granger Microsoft data center site. The St. Joseph County Drainage Board recently unanimously approved a contractor’s request to dewater or drain the land along Bittersweet and Cleveland roads so they can install Mishawaka Utilities water and sewer lines. HRG Construction will perform the dewatering for 40 days, from February 26 through April 2.