Architect: Early learning center will be done in mid-May 2026
By Savannah Hess Correspondent,
2025-03-01Work to transform a portion of Pasquotank Elementary School into a new learning center for Elizabeth City-Pasquotank Public Schools pre-kindergartners won’t be finished until mid-May of next year.
That’s according to a proposed timeline for the project by the architectural firm hired to design Elizabeth City-Pasquotank Public Schools’ new Early Childhood Learning Center at the former elementary school.
The ECPPS Board of Education voted unanimously Monday, Feb. 24, to move forward with Rocky Mount-based Oakley Collier Architects’ engineering and design proposal for the new learning center. Oakley Collier, who was awarded the learning center contract last October, will be paid a lump sum of $141,800 in professional fees.
Ann Collier, managing partner in Oakley Collier, said her company’s proposal covers all the engineering and architectural services needed for the learning center project, including bidding, construction administration “from tonight until you open the school and after that as needed.”
“We would be handling architecture, engineering, all of the engineering disciplines, including fire protection,” she said. “We would look at building codes, the structural capacities — ‘the bones’ we call it — of the building, HVAC, air-conditioning, heating, fire alarms — all of the life safety things — as well as all of the programs required to put in an early learning center on this campus.”
Citing ECPPS’ loss of 1,000 students over the past decade, the school board voted last year to close Pasquotank Elementary at the end of the 2023-24 school year and reassign its students to other schools. The board also agreed with the district’s plans to convert the former school into an early childhood learning center for preschoolers. The district’s pre-K program is currently housed in 10 classrooms at Sheep-Harney Elementary. Once open, the district’s pre-K program will be run solely at the early childhood center.
Currently the former Pasquotank Elementary School is used for office space and is the home of the district’s child nutrition offices. It’s also used for professional development programs.
According to Oakley Collier’s proposal, the early learning center will occupy between 22,000 and 25,000 square feet in two wings of former school — “about half the school,” Collier told the school board. That includes space for a kitchen as well as for the existing lobby and front offices. There also will be “community support space(s)” created near the lobby for public use.
Oakley Collier’s plan calls for a minimum of 10 pre-K/early childhood classrooms, although 12 is the preferred number. The plan also envisions office for early childhood staff, spaces for staff support, an expansion to the building’s existing kitchen for additional office, storage and support spaces, and access for the early childhood program’s access to the building’s existing media center.
Collier explained in a Jan. 19 letter to Wilma Jordan, ECPPS director of facilities, that the project will be completed in two phases: a preliminary design and budgeting phase, and once that’s approved, a bidding and construction phase.
Collier told school officials that her firm’s design team performed an on-site walkthrough of the school building and met with district staff in early January. She said the on-site visit was important, not just to confirm existing conditions and understand the scope of the project but also to get a sense of officials’ vision for the new center.
“For us to understand what it is you need, we want to make sure we see and touch and feel and understand the scope and vision,” she told the school board. “We understand there’s a rich history here at this school. ... (We want) to honor (that), to make sure we keep that intact. We place importance on that, and understand the project of an early learning center is an exciting one.”
Collier said in her letter to Jordan that the first phase of the project will include developing an “overall space summary” for the learning center. The summary will be based on N.C. Department of Public Instruction standards for preK/early childhood programs and the “budget dollars available” the district has for the project, she said. Collier Oakley also will develop a preliminary conceptual floor plan and site design that will include any needed parking or playground improvements.
The school district will use $1.70 million in county funds to make the renovations. The money is coming from an overall request of about $2.63 million in school capital reserve funds approved by the Pasquotank Board of Commissioners in August.
The first phase of the project also will include developing a preliminary project budget and preliminary project schedule. That schedule currently calls for releasing requests for proposals to general contractors on June 8 and receiving RFPs back on June 28; getting NCDPI approval of the estimated bid for the center on July 18; advertising construction bids for the center on July 22 and getting them back on Aug. 19; and the Board of Education approving the bids on Aug. 26.
After a contract with the general contractor is signed Sept. 15, construction would begin and be completed by May 15, 2026.
“We did talk about how soon we can get it open,” Collier told the school board. “Unfortunately, without knowing all of the things we need to address on the state level with reviews, I don’t believe this fall is achievable in this schedule to get this renovation done. But it won’t take as long as next fall.”
She said the timeline Oakley Collier has offered covers “from day one” of the project to “move-in” and includes time for the district to equip the center with furniture and other services.
ECPPS board member Angelique “Angie” Boylan did not attend the Feb. 24 meeting.
Former Daily Advance Managing Editor Julian Eure contributed to this report.