Highway: US 51, from the Marathon County line to Lincoln County K (Exit 211) in Merrill
Schedule: Completion by Nov. 15
Project ID: 1176-22-72/73
Project description: Crews will remove the existing asphalt surface and crushed concrete and then replace them with base materials and asphalt pavement; complete minor grading at median crossovers for traffic control; repave maintenance crossovers and interchange ramps; and add additional guardrail on northbound US 51 at WIS 64.
Anticipated work scheduled: Crews will be adjusting and repairing guardrail along the southbound US 51 lanes.
Traffic impacts: Motorists can expect one lane of southbound US 51 to be closed from County K to the Wisconsin River from 6 a.m. Wednesday, July 6 to 6 p.m. Saturday, July 9. The outside shoulder on northbound US 51 from the Marathon County Line to County K will also be closed.
Website: https://projects.511wi.gov/us51nbsb/

Highway: WIS 107, at the bridge over Little Pine Creek between Hillcrest and Dotter Roads
Schedule: June 15 to Aug. 17
Project ID: 9305-09-73
Project description: Crews will replace the existing structure with a bridge that will provide proper clear width and upgrade the existing guardrail to meet current standards.
Anticipated work scheduled: Crews will begin forming the floor of the box culvert and placing reinforcements. Crews will then begin pouring concrete.
Traffic impacts: WIS 107 is closed to through traffic at Little Pine Creek, and traffic is being detoured via County J, US 51 and County S.
Website: https://projects.511wi.gov/wis107littlepinecreek/

Highway: County Highway E
Schedule: Tuesday, July 5, 2022, beginning at 7:00 a.m. to Monday, July 11, 2022 at 4:30 p.m.
Project description: The Bridge is over the New Wood River is being repaired.
Traffic impacts: The County Highway E bridge between Brooks Road and Wangen Road in the Town of Harding will be closed to ALL TRAFFIC, due to bridge repair. The Bridge is over the New Wood River.

Highway: County Highway D
Schedule: Tuesday, July 5, 2022, at 7:00 a.m. until further notice
Project description: Extensive road work on County Highway D
Traffic impacts: County Highway D in the Town of King and Harrison will be closed between County Highway B and US Hwy. 51. LOCAL TRAFFIC ONLY.