Share
Work started last week on raising the B.F. Sisk Dam at San Luis Reservoir 10 feet to reduce the risk of the massive earthen structure collapsing in a major earthquake.
This comes after exploratory blasting began in spring 2020 at the reservoir adjacent to Highway 152 near Los Banos.
The federal project is expected to cost $1.1 billion and take nine years — even with crews working 24 hours a day beginning later this year. Altogether, more than 10 million cubic yards of rock, gravel, and soil will be moved from nearby hills to harden and raise the now 382-foot high dam.
But, with the drought increasing the need to expand water storage in big precipitation years for ag and urban users alike, some are asking, “Why not raise the dam 20 feet instead?”
10 More Feet Will Cost $1 Billion
That additional 10 feet would cost another $1 billion, and increase the reservoir’s capacity by 130,000 acre-feet. There are farmers and potentially interests in the Santa Clara Valley who might be willing to pay the freight.
Read more from reporter Paul Rogers of the Bay Area News Group at this link.
Here is the link to the Bureau of Reclamation’s fact sheet about the project.
RELATED TOPICS:
Tabloid Publisher Says He Pledged to Be Trump Campaign’s ‘Eyes and Ears’ During 2016 Race
9 hours ago
General Motors Reports Strong First-Quarter Profits as Prices Help Offset Small US Sales Dip
9 hours ago
Caitlin Clark Is Set to Sign a New Nike Deal Valued at $28 Million Over 8 Years, Reports Say
10 hours ago
A Far-Right German EU Lawmaker’s Aide Is Arrested on Suspicion of Spying for China
10 hours ago
Wall Street Rallies and Adds to Its Hot Start to the Week
10 hours ago
Tent Compound Rises in Southern Gaza as Israel Prepares for Rafah Offensive