Major Roadwork Scheduled Friday, April 8 Through Thursday, April 14
The following scheduled roadwork has been verified at the time of release. Please keep in mind work is weather permitting and subject to change. For updates to this list, visit: QuickMap at http://quickmap.dot.ca.gov, check the California Highway Information Network (CHIN) at https://roads.dot.ca.gov or call 1-800-GAS-ROAD (1-800-427-7623). For information pertaining to emergency roadwork, check QuickMap and the CHIN. For media updates, please contact the appropriate Public Information Officer listed above.
Del Norte County
U.S. 101 (8.3/8.6) – Bridge work north of Klamath near Old Hunter Creek Road will continue. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays. LC#C101KB
U.S. 101 (14.9/22.7) – Emergency work and construction in the Last Chance Grade area will continue. One-way traffic control will be in effect. Motorists should anticipate 15-minute delays at all hours. LC#C101FA and C101OC
U.S. 101 (25.5/27.6) – Shoulder work near Ocean World in Crescent City will continue. Lane closures will be in effect from 6:30 a.m. to 6:30 p.m. Motorists should expect minor slowdowns through the area. LC#C101SA
U.S. 199 (4.2/4.4) – Bridge work at Hiouchi Bridge will occur starting Tuesday, April 12. One-way traffic control will be in effect from 6:00 a.m. to 6:00 p.m. Motorists should expect minor slowdowns through the area. LC#C199BA
U.S. 199 (12/12.2) – Bridge work at Mary Adam Peacock Bridge will occur starting Tuesday, April 12. One-way traffic control will be in effect from 6:00 a.m. to 6:00 p.m. Motorists should expect minor slowdowns through the area. LC#C199BA
Humboldt County
Route 36 (0/1.7) – Construction near the 101 junction will continue. One-way traffic control will be in effect from 7 a.m. to 7 p.m. weekdays. Motorists should anticipate 5-minute delays. LC#C36AA
Route 36 (16.8/17.9) – Electrical work from Abe Wouk Memorial Grove Road to Van Duzen River Bridge will continue. One-way traffic control will be in effect from 6 a.m. to 7 p.m. weekdays. Motorists should expect 10-minute delays. LC#C36JA
U.S. 101 (17.9) – Bridge work south of Phillipsville will continue. Lane closures will be in effect weekdays. Motorists should anticipate minor traffic slowdowns. A northbound onramp closure will also be in effect. Motorists should use an alternate route. LC#C101FB
U.S. 101 (27.7) – Bridge work at South Fork Eel River Bridge will continue. Lane closures will be in effect weekdays from 6 a.m. to 8 p.m. Motorists should anticipate minor traffic slowdowns. LC#C101CF
U.S. 101 (49.2/52) – Electrical work from Shively Road to Eel River Bridge Overhead will occur starting Monday, April 11. Northbound and southbound lane closures will be in effect from 6 a.m. to 7 p.m. Motorists should expect 10-minute delays. LC#C101QA
U.S. 101 (91.5) – Tree work at the Route 101 School Road Overcrossing will occur Friday, April 8. Lane closures will be in effect from 8:30 a.m. to 5 p.m. Motorists should expect 10-minute delays. A northbound offramp closure will be in effect. Motorists should use an alternate route. LC#M101BA
U.S. 101 (114.5/116.9) – Bridge work from McDonald Creek Bridge to Old Stage Road will continue. One-way traffic will be in effect weekdays from 7 a.m. to 3:30 p.m. Motorists should expect 5-minute delays. LC#C101QC
U.S. 101 (19.8/21.4) – Emergency work will occur on Wednesday, April 13. One-way traffic will be in effect from 7 a.m. to 7 p.m. Motorists should expect 5-minute delays. LC#P169AA and P169BA
Route 255 (3.7/4) – Construction near Manila will continue. A southbound shoulder closure will be in effect from 7 a.m. to 5 p.m. weekdays. Motorists should expect minor traffic slowdowns. LC#C255CA
Route 255 (2/5.1) – Permitted utility work from Samoa to Arcata will continue. One-way traffic will be in effect from 7 a.m. to 6 p.m. weekdays. Motorists should expect 10-minute delays. LC#C255BA
Route 299 (1.8) – Construction near Route 200 will conclude on Friday, April 8. Lane closures will be in effect from 7 a.m. to 6 p.m. weekdays. Motorists should expect minor traffic slowdowns. LC#C299CA
U.S. 299 (3.8/4) – Tree work will occur on Monday, April 11. Lane closures will be in effect from 7 a.m. to 6 p.m. Motorists should expect minor traffic slowdowns. LC#P299AA
Route 299 (7.4/11) – Construction east of Blue Lake will conclude on Friday, April 8. One-way traffic control will be in effect from 7 a.m. to 5 p.m. weekdays. Motorists should anticipate 10-minute delays. LC#C299EB
Route 299 (17.2/20.7) – Emergency work west of the Burney Vista Point will continue. One-way traffic control in effect 7 a.m. to 5 p.m. Motorists should expect 15-minute delays. LC#C299MA
Route 299 (28.4/30.6) – Tree removal from Cedar Creek Road to Vista Point will conclude on Friday, April 8. One-way traffic control will occur from 7 a.m. to 5 p.m. weekdays. Motorist should anticipate up to 15-minute delays. LC#C299MA
Route 299 (34.6/37.9) – Drainage work near Willow Creek will continue. One-way traffic control will be in effect from 7 a.m. to 3:30 p.m. weekdays. Motorists should expect 10-minute delays. LC#C299AB
Lake County
Route 20 (18/18.8) – Drainage work continues in Lucerne near Oak Crest Avenue. One-way traffic control will be in place from 7 a.m. to 5 p.m. weekdays. Motorists should expect 10-minute delays. LC#C20AB
Route 20 (23.9/28) – Road work in Glenhaven near Oak Grove Avenue will begin on Friday, April 8. One-way traffic control will be in effect from 7 a.m. to 7 p.m. weekdays. Motorists should anticipate 15-minute delays. LC#C20CB
Route 20 (37) – Bridge work at Cache Creek is scheduled to begin on Tuesday, April 12. One-way traffic control will be in effect from 5 p.m. to 6 a.m. weeknights. Motorists should anticipate 5-minute delays. LC#C20CA
Route 29 (9.7) – Bridge work continues at Putah Creek. One-way traffic control will be in effect from 9 p.m. to 6 a.m. weeknights. Motorists should anticipate 5-minute delays. LC#C29HA
Route 29 (20.3) – Bridge work at Siegler Creek continues. One-way traffic control will be in effect from 9 p.m. to 6 a.m. weeknights. Motorists should anticipate 5-minute delays. LC#C29HA
Route 29 (22.1) – Road work will occur in Lower Lake at Point Lakeview Road on Tuesday, April 12. One-way traffic control will be in effect from 7 a.m. to 5 p.m. Motorists should anticipate 5-minute delays. LC#C29GA
Route 29 (27.9/32) – Road work is scheduled to begin near Red Hills Road on Monday, April 11. One-way traffic control will be in effect. Motorists should anticipate 15-minute delays. LC#C29FA
Route 29 (52.1) – Bridge work at Scotts Creek will conclude on Friday, April 8. One-way traffic control will be in effect from 12 p.m. to 8 p.m. Motorists should anticipate 5-minute delays. LC#C29HA
Mendocino County
Route 1 (34.9/35.9) – Utility work is scheduled for Friday, April 15 north of Elk. One-way traffic control will be in effect from 9 a.m. to 4 p.m. Motorists should expect 5-minute delays. LC#P1FA
U.S. 101 (5/5.9) – Slide removal at Pieta Creek Bridge will continue. Northbound Lane closures will be in effect. Motorists should anticipate 5-minute delays. LC#C101KC
U.S. 101 (12/13.2) – Tree work will occur in Hopland near Road 112 on Tuesday, April 12. One-way traffic control will be in effect from 9 a.m. to 5 p.m. Motorists should expect 5-minute delays. LC#P101FA
U.S. 101 (23.4) – Bridge work in Ukiah at Route 222 will begin on Monday, April 11. Lane closures will be in effect from 7:00 a.m. to 5:00 p.m. weekdays. Motorists should expect minor slowdowns through the area. LC#101UB
U.S. 101 (24.5/25.7) – Road work at the East Perkins Street Overcrossing in Ukiah will begin on Monday, April 11. Lane closures will be in effect from 7:00 a.m. to 5:00 p.m. weekdays. Motorists should expect minor slowdowns through the area. LC#101UB
U.S. 101 (59) – Moss Cove Safety Rest Area will be closed through July 2022. LC#C101TB
U.S. 101 (82.5) – Empire Camp Safety Rest Area will be closed through July 2022. LC#C101TB
Route 128 (29.5) – Tree work will occur in Boonville near Hutsell Road on Tuesday, April 12. One-way traffic control will be in effect from 9 a.m. to 5 p.m. Motorists should expect 5-minute delays. LC#P128AA
Route 162 (11/12.6) – Electrical work continues south of Dos Rios near the Rodeo Creek Bridge. One-way traffic control will be in effect from 7:00 a.m. to 3:30 p.m. weekdays. Motorists should expect up to 10-minute delays. LC#C162IA
Route 175 (0.1/2.7) – Tree work in Hopland near Old Toll Road will occur on Wednesday, April 13. One-way traffic control will be in effect from 9 a.m. to 5 p.m. Motorists should expect 5-minute delays. LC#P175DA
Route 175 (0.1/1) – Utility work is scheduled for Friday, April 8 in Hopland near First Street. One-way traffic control will be in effect from 9 a.m. to 5 p.m. Motorists should expect 5-minute delays. LC#P175DA
Route 253 (0.1/0.5) – Tree work is scheduled for Tuesday, April 12 in Boonville near Route 128. One-way traffic control will be in effect from 9 a.m. to 4 p.m. Motorists should expect 5-minute delays. LC#P175DA
*Items in bold indicate updates from the previous week
Join the discussion! For rules visit: https://kymkemp.com/commenting-rules
Comments system how-to: https://wpdiscuz.com/community/postid/10599/
Thanks for the update…