Harlingen reviewing data center water contract
By Fernando Del Valle,
12 days agoH ARLINGEN — After months of public protest, officials here are reviewing a WaterWorks agreement to determine if the city has grounds to challenge the contract residents argue could sell off drinking water to a data center for as long as 50 years.
A year after WaterWorks’ board of directors’ unanimous approval, city commissioners are questioning the terms of the contract which could sell treated sewer water along with potable water, including the contract’s setting of water rates.
Under the agreement tied a proposed 1,785-acre data center campus outside Harlingen’s city limits, WaterWorks would provide RGV Property Group with up to 4.6 million gallons of treated sewer water a day while requiring the agency supplement potable water in cases in which effluent amounts fall short.
Among the city’s concerns, questions surround the contract’s clause offering RGV Property Group water at a rate charged to customers within the city limits, while the City Charter gives the city commission the sole authority to set water rates, City Attorney Mark Sossi said Tuesday.
“The city is looking at its legal options,” he said.
Now, under WaterWorks’ rate schedule, the agency charges commercial customers within the city limits a rate of $1.83 per 1,000 gallons while charging commercial customers outside the city limits a rate of $2.75 per 1,000 gallons.
Meanwhile, the contract offers RGV Property Group a rate of 75 cents per 1,000 gallons of effluent water.
In September 2025, the WaterWorks board, based on then-interim General Manager Roy Rodriguez’s recommendation, approved the contract which would sell water for about $1.2 million a year.
While WaterWorks’ board President Michael Garza referred questions to new General Manager Marie Leal, she did not respond to messages requesting comment.
Meanwhile, Gene McCullough, the attorney representing WaterWorks, could not be reached for comment.
“We’re looking at all options available to us,” Mayor Norma Sepulveda said, adding officials are reviewing the “possibility of reworking WaterWorks’ contract.”
Commissioners are questioning the terms of the contract.
“I don’t think it’s a good contract. I don’t like the options it gives the data center,” Commissioner Rene Perez said in an interview. “I don’t like long-term contracts. We won’t know what the city’s going to be like in 50 years. For Waterworks to be beholding to any entity for 50 years is something I would have never done. I hear the public complain about the water contract. The people’s complaints have valid points.”
Commissioner Frank Morales described the agreement as “a highly irregular and questionable contract.”
“I see it as a one-sided agreement,” he said, questioning the contract that could lock WaterWorks to 50 years of water sales.
Under the contract, WaterWorks’ water sales would run “20 years from the commercial operations date and, unless otherwise terminated in accordance with the terms of this agreement, shall automatically be extended for two additional terms of 15 years each.”
“Will the cost of effluent water be the same in 20 years, will the price of effluent water be the same in 35 years, will the price of effluent water be the same in 50 years?” Morales asked.
For months, residents have called on commissioners to review the contract’s terms and conditions.
During a Sept. 24 town hall meeting, resident Luis Valdespino questioned the contract’s clause which offers RGV Property Group water at a rate charged to customers within the city limits while the City Charter gives the commission the authority to set water rates.
“That conversation is ongoing, specifically on that point you’re addressing,” Commissioner Daniel Lopez responded.
Under a contract clause, RGV Property Group “agrees to pay WaterWorks $0.75 per 1,000 gallons of the contracted amount of reclaimed water,” describing the rate as “the reclaimed water rate.”
Meanwhile, the contract includes portable water rates.
“The rates charged by WaterWorks for any portable water supplied to RGVPG to supplement the lack or shortage of will be the then-current applicable commodity charge for inside city limits commercial accounts as adopted by the governing body of the city for all users, multiplied by the actual quantity of potable water taken,” the contract states.
“Regardless of the reason for the WaterWorks not providing sufficient reclaimed water to meet RGV Property Group LLC.’s requirements, and notwithstanding anything herein to the contrary, the charge for potable water will be the commodity rate for inside city limits commercial potable water accounts established by the city commission,” it states.
The contract also requires WaterWorks to sell effluent water at a specific “quality” complying with the Texas Pollution Discharge Elimination System permit’s “concentrations and conditions.”
“If variations occur from the maximum parameters …, WaterWorks shall supplement with potable water until the reclaimed water is under the maximum levels …,” the contract states.
“Notwithstanding anything stated herein to the contrary, the parties agree that the contract quantity of water will be sourced first from reclaimed water,” the contract states. “In the event and to the extent that the quality of the reclaimed water fails to meet the requirements specified in this agreement, or WaterWorks is prevented from providing reclaimed water due to the failure to satisfy any regulatory requirement applicable to WaterWorks, then WaterWorks will make available to RGVPG such sufficient quantities of potable water to meet RGVPG’s requirements up to but not exceeding the contract quantity or water.”