Data Center Alley

Plans to relax regulations on how often data centers in the region can run their backup diesel generators have been narrowed to only relax those rules in Loudoun.

Data centers, which seek to have as little downtime as possible, have backup diesel generators onsite which typically are permitted to start monthly for testing. The state estimates there are 4,151 such generators at data centers in Loudoun. Based on the state’s estimates those generators collectively put out almost 93 tons of non-methane hydrocarbons and nitrogen oxides per hour of runtime—potent and poisonous greenhouse gases. Other pollutants include almost 51 tons of carbon monoxide per hour.

Dominion Energy last summer warned data center companies that its electricity grid may not be able to supply power to new data centers—but the proposed order from the Virginia Department of Environmental Quality now suggests it may not even be able to power existing data center projects during the peak electricity usage months of summer.

“DEQ is concerned that Loudoun County is an area in which there may not be a sufficient amount of electricity for data centers due to severe, localized constraints in electricity transmission,” a public notice from the state agency reads. “A transmission constraint issue exists in the area which may affect the ability to provide enough electricity to data centers through 2025. In particular, the period between March and July 2023 has been identified as a time of potentially acute stress on the transmission capacity of the grid.”

However the DEQ's notice also said the proposal is "a purely precautionary measure" and "we do not anticipate that any data center will need to use this variance." It also wrote any such activations would likely only affect smaller areas, and data centers would not be expected to turn on all of their generators, since many are redundant backups.

The proposal would allow data centers to run their generators when PJM Interconnection, the company that coordinates power transmission in Virginia, issues an alert about possible capacity problems in the electrical grid. Data center operators would also be required to provide a calculation of the air pollution they generated during that time “as soon as practicable.” The variance would expire at the end of July.

Previously, that variance applied to data centers in Loudoun, Prince William and Fairfax counties; a second draft removed the other two counties and would apply only to Loudoun.

“DEQ takes the public participation process very seriously and is making appropriate revisions to the proposal based on that input,” DEQ Director Michael Rolband stated.

The new notice for the first time included the state’s estimates of those generators’ output of air pollutants. With the revised proposal, the state has scheduled a new public hearing on April 6, although not in Loudoun County, and at 11 a.m. on a weekday. The hearing is scheduled at the DEQ Northern Regional Office in Woodbridge at 11 a.m. Thursday, April 6.

A public comment period, which had previously been set to expire March 14, was also extended until April 21.

The state proposal stirred concern from the Piedmont Environmental Council, which has scheduled a public meeting about the proposal at the Ashburn Library at 6 p.m. on March 28. The council’s announcement said the proposal “is not only short-sighted in addressing the grid constraints, but it has the potential to do real damage.”

“Many of our schools, sports fields, playgrounds and homes are located near data center complexes, and there is real potential for localized air pollution and regional greenhouse emissions with the increased use of these diesel generators,” the council wrote. “Air pollutants such as ozone and particulate matter increase the amount and seriousness of lung and heart disease and other health problems, particularly for children, the elderly and those with pre-existing conditions (asthma, pregnancy, COPD, etc.).”

The full proposal is online at deq.virginia.gov/get-involved/topics-of-interest/data-centers-public-comment, or deq.virginia.gov/permits-regulations/public-notices/air under “REVISED Order and local variance for data centers – Loudoun County, VA.”

The DEQ accepts written comments by email, fax, and mail. Comments must include the full name, address and telephone number of the person commenting. To comment, request public documents or for other information contact Karen G. Sabasteanski, Office of Air Data Analysis and Planning, Department of Environmental Quality, PO Box 1105, Richmond, VA 23218. Call 804-659-1973 or fax 804-698-4510, or email karen.sabasteanski@deq.virginia.gov.

A DEQ public hearing is scheduled in the conference room of the agency’s regional office at 13901 Crown Court, Woodbridge, at 11 a.m. on Thursday, April 6.

This article was updated March 21 at 5:20 p.m.

Sign-up for our Newsletters!

(14) comments

DaveBase

Wow. Did we not understand how data centers worked when we issued all the approvals?

timjweaver

so the VDOE is moving to approve the increased use of 4000+ diesel generators during PEAK time? This couldn't this be because peak time is more expensive to the corporations? Surely not. Dominion states they will not be able to support power requirements of these facilities through 2025. The amount of pollution is already increasing in Loudoun due to construction, airport traffic etc. This needs to be blocked by residents immediately.

disappointedloudouner

Perhaps we should abolish electric cars in Loudoun County so the power grid can supply enough power to the data centers.

Downtowner

Battery storage technology should be considered for these data centers instead of dirty-diesel generators. Charge up when electricity is abundant (typically deep night) and use for grid stabilization during peak (or as back up in an outage). As costs have decreased and technology improved, these utility-scale battery projects are becoming the solution to grid stability/back-up power for entire communities in many places.

ace10

Fact Check: Loudoun's datacenters consume up to 3 gigawatts (3000 megawatts) of electricity each day.

The world's largest battery power storage facility, Moss Landing in California, has a capacity of 400 megawatts.

NoVacommentator

I couldn't care less. These data centers have brought in huge tax revenues and in the 16 years that I have lived in Ashburn I have noticed no change in the air. It is very clean. Plus they are handsome buildings. They take up space that was once covered in ugly brush.

ace10

Parody?

Clamb

Meanwhile, kerosene burning jets take off and land over Loudoun around the clock.

Weevil

whataboutism...check

uuplink

The solution to this problem is simple: build the new data centers close to the sources of generation. Dominion is gaming the system as it always does to promote the construction of new power lines across our communities. Loudoun County will receive less tax revenue too bad. Homeowners will not have their property values destroyed by power lines to enrich “cloud” service providers.

Chris Manthos

4100 commercial generators in LoCo? Provides for a lot of local options when the grid fails permanently.

java1981

Once again our BoS got pushed around. They thought they were doing Loudoun a favor by bringing in these eyesores. Now they will be releasing more pollutants across the county. Is this what you were hoping for Loudoun when you voted these clowns in? In the end, they keep on approving data center after data center because it gave them more money to spend on their pet projects while still raising taxes on us residents. Now we have to deal with worsening air quality, and whatever else these things spew out onto the community.

Thanks BoS! You are doing a swell job!

ace10

DEQ will prevent you from driving to work or the doctor's office if your vehicle is even marginally over the totally-arbitrary emissions limits.

Dominion will brown your house out when demand from data centers outpaces supply.

How long until we're all nothing more than Soylent Green?

Weevil

This is the start of the slippery slope where these giant polluting eyesores continue to be year-over-year worse deal for Loudoun than they were the year before. If you live anywhere near one of these behemoths (and thanks to the slapdash nature of Loudoun zoning you likely do) you should speak up to ensure this relaxation of sensible regulations DOES NOT occur.

Welcome to the discussion.

Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.