Plan for these construction projects affecting traffic, parking around UK campus

By Valarie Honeycutt Spears,

14 hours ago
https://img.particlenews.com/image.php?url=12DnWy_1HVtVwre00
A University of Kentucky sign facing Limestone Avenue on June 12, 2026, in Lexington, Ky. Tasha Poullard/tpoullard@herald-leader.com

Several construction and utility projects will affect traffic, parking and transit around the University of Kentucky campus through early December.

Drivers should allow extra travel time and watch for changing traffic patterns, particularly around Woodland Avenue, South Upper Street and south campus, UK said in a news release.

Woodland Avenue closure — Nov. 23-Dec. 4

Woodland Avenue will be closed just south of Euclid Avenue from 9 a.m.-3 p.m. daily through Dec. 4. The closure started Nov. 23, and will allow crews to connect sanitary and water lines for the Woodland Village construction project.

Traffic will be detoured toward Rose Lane and Rose Street.

Woodland Avenue will remain open all day Saturday, Nov. 28, for the UK-Louisville football game.

KTRDC parking lot closure

The KTRDC parking lot closed starting Nov. 23 for ongoing work on the south campus steam and chilled-water utility project. The closure is expected to continue through approximately mid-February.

South Upper Street lane shift — Beginning Nov. 25

Beginning Nov. 25, raffic on South Upper Street just south of Cornerstone Garage was shifted west around a construction area associated with the university’s Central Heating Plant boiler project.

Both southbound travel lanes are still open. However, the southbound bicycle lane has been temporarily eliminated and several on-street parking spaces are unavailable. The traffic pattern is expected to remain in place for about two months.

University Drive closure remains in place

Drivers should also be aware that the existing closure on University Drive remains in place as utility and infrastructure work continues. The section between Complex and Hospital drives is expected to reopen in mid- to late December. The portion south of Hospital Drive is expected to remain closed into spring 2027.

Motorists, bicyclists and pedestrians should use caution in construction areas, follow posted signs and allow additional time when traveling near campus.

UK provides more information on its transportation website.