PJM reviewing potential changes to interconnection reliability requirements

By Dave Kovaleski,

2026-08-14
https://img.particlenews.com/image.php?url=2oKesD_1EF3QSFD00

PJM Interconnection is evaluating potential changes to interconnection reliability requirements related to ride-through standards and practices for large loads, like data centers and crypto-mining facilities.

This comes after PJM saw nearly 4,000 MW of data center load trip offline unexpectedly in Virginia on July 22. It was the largest such event in PJM history. While the grid did not experience significant reliability impacts, it did experience a high imbalance between generation and load and large swings in voltage and frequency.

PJM and Dominion operators quickly took action, as data centers disconnected from the grid and switched to backup generation in reaction to a system fault.

According to Dominion’s investigation, at 7:56 a.m. on July 22, a mechanical failure caused a 230 kV line to be automatically removed from service in Northern Virginia. As the fault was properly removed from the system, data centers in the Dominion zone unexpectedly disconnected from the grid. This caused spikes in voltage and system frequency.  The first load drop of 2,970 MW took place when data centers started to transfer away, and system voltage increased, according to Brian Starling, Director, System Operations Center for Dominion Energy.

When these first large loads transferred to backup generation, the loss of their loads prompted high system voltage disturbances. In response, a second wave of 1,099 MW of data centers disconnected and transferred to on-site backup generation. In all, roughly 3,800 MW of large load disconnected and transferred without warning.

Overall, PJM observed a load drop from 99,984 MW to 96,205 MW. The PJM Control Center quickly dispatched generation down to balance the large change between generation and load, to restore system frequency to 60 Hz and maintain grid stability. PJM recovered within nine minutes, well within the regulatory standard of 30 minutes, dispathcing reactive power resources to lower system voltage.

While the July 22 event was the largest large loads transfer PJM has experienced, similar events have occurred in the Dominion zone. Two events on Feb. 17, 2025, and July 10, 2024 caused sudden load transfers of about 1,500 MW each.

“This was a normally cleared fault,” Operating Committee Chair Emanuel Bernabeu said. “They should not disconnect from the grid. These data centers are too sensitive to the kind of voltage that they like, and we feel they are disconnecting too early.”

PJM and its stakeholders approved voluntary ride-through guidelines for these generation resources in 2019. But now the system is facing ride-through challenges on the load side. Going forward, PJM and Dominion will continue to jointly review the event and system impacts with an eye to stakeholder coordination for new standards.

“We are currently evaluating potential enhancements to reliability requirements, with consideration of existing and future industry ride-through standards and practices,” Matthew Wharton, PJM manager – reliability engineering, said.

Computational loads on the grid, which include data centers, crypto mining facilities and others, set their protection system to monitor for sudden change or abnormal voltage levels and may rapidly switch to on-site backup generation in response to grid events, even during routine disturbances that are correctly cleared by transmission protection systems. This can create reliability issues for the grid because unexpected Large Load transfers from the PJM system have two effects on the system.

The North American Electric Reliability Corporation (NERC) has defined “computational load” as “load comprised of power demand from information technology equipment, such as servers, storage, and networking hardware.” As it stands, computational loads are not subject to NERC Reliability Standards, and computational loads are not a NERC-registered entity.

However, on July 16, the Federal Energy Regulatory Commission ordered NERC to define and create the first phase of enforceable Reliability Standards needed to manage reliability risks posed by computational loads. FERC ordered NERC to submit the first phase of new enforcement provisions by Dec. 31. However, this first phase will not address the minimum voltage or frequency ride-through requirements for computational loads. Those requirements are expected to be included in NERC Reliability Standards in 2027.

The post PJM reviewing potential changes to interconnection reliability requirements appeared first on Daily Energy Insider.