Canton, Cherokee County considering parking deck agreement

By ejohnson,

23 hours ago
https://img.particlenews.com/image.php?url=3R1sU9_1HNhlOVc00
A concept rendering shows what the proposed North Street development could look like. By Goodwyn Mills Cawood

The Canton City Council is considering an intergovernmental agreement between the city, the Canton Downtown Development Authority and Cherokee County to build a parking deck on North Street in downtown Canton.

The city council heard a presentation from Canton Assistant City Manager Nathan Ingram Thursday.

The council is scheduled to make a decision on the proposed agreement Dec. 3, with a vote by the DDA to follow during its December meeting, Ingram said.

The Cherokee County Board of Commissioners is scheduled to consider the agreement Dec. 15.

The planned 800-space parking deck will serve the North Street Gateway Development Project, the Cherokee County Justice Center and the general downtown area, according to the city.

The county’s projected minimum parking need in the deck for the Cherokee County Justice Center and the expansion is 400 spaces, according to city documents.

Ingram told the Tribune that the city and county are looking to split the overall cost of the parking deck; however, the IGA "involves some give and take."

"While splitting the actual costs evenly may be difficult to work out, there will be compromises throughout the overall project," he said. "For example, the DDA owns the vast majority of the land for the proposed annex and parking structure, which must be taken into consideration."

Under the proposed agreement, the county would contribute $18 million in Special Purpose Local Option Sales Tax funding to help fund the construction of the parking deck. The majority, $14.2 million, would go toward 400 parking spaces at an estimated cost of $35,500 per space.

The county’s proposed cost breakdown is:

$14.2 million for 400 parking spaces$2.9 million to go toward site development costs$500,000 for the security vestibule at the Justice Center rear entrance from the parking deck$400,000 county-controlled contingency

A city staff report says the project cost is $30 million, but Ingram said the actual total cost will be higher than that.

"While the estimated cost for the precast parking deck alone is just over $30 million, the total cost will be higher once you include sitework, engineering, architectural design, land acquisition and other related expenses," Ingram told the Tribune. "This is reflected in the proposed IGA. The county's $18 million breakdown notes their half of the parking deck cost at $14.2 million and their half of the site development costs at $2.9 million. Combining these with the city's equal portion brings the total project cost to well over $30 million."

Ingram added that the Canton DDA anticipates financing the city's portion through the use of revenue bonds.

"Additionally, as this project is located within the city's tax allocation district, potential financing opportunities for public infrastructure will also be available," he said. "Details regarding the final financing structure have yet to be determined. This will ultimately depend on agreement by all parties, final project costs, and other related factors."

While the city and county continue planning the parking dark, additional parking for the Cherokee County Justice Center campus and historic Cherokee County Courthouse is on the way.

Commissioners voted in August to create 220 new parking spaces behind two buildings along North Street. Construction has started and is expected to be completed in the first quarter of 2027.

There are currently 132 parking spaces behind the courthouse and other North Street buildings.

In addition to the parking deck, the North Street Gateway Development Project will include a four-story expansion and renovations to the Cherokee County Justice Center, a new county government annex, two mixed-use buildings with apartment units above office space, a boutique hotel, an office building, an 800-space parking deck, commercial and retail space.