Construction project in Central to move forward in August

City officials in Central Louisiana have announced that after a five-year wait, they are finally ready to move forward with the expansion of Sullivan Road.
Published: Jun. 1, 2023 at 7:02 PM CDT|Updated: Jun. 2, 2023 at 10:12 AM CDT

CENTRAL, La. (WAFB) - City officials in Central Louisiana have announced that after a five-year wait, they are finally ready to move forward with the expansion of Sullivan Road.

Mayor Wade Evans is thrilled to have worked with Mayor-President Sharon Weston Broome in Baton Rouge and other agencies to begin the project.

The project aims to ease traffic between Hooper and Wax Road. It has faced several delays due to engineering issues. Mayor Evans said that the city had to redo the sewer since Central has a water table that is very close to the surface.

“They redid the sewer. Out here in Central, we have a water table that is very close to the surface. So the one size fits all approach design they did just doesn’t work out here,” Mayor Wade Evans said.

Despite the setbacks, Mayor Evans expressed his excitement about the project, saying that the delays allowed them to learn what wouldn’t work from an engineering standpoint.

Evans confirmed that construction plans are set to begin in August of this year.