MBTA announces 2027 schedule, promising fewer shutdowns
By Samantha Genzer,
16 hours agoThe agency said it plans to focus on signal upgrades, track repairs, and accessibility improvements.
3 minutes to read
The MBTA plans to carry out 100 days of service disruptions next year, a slight decline from this year, the transit agency announced Thursday.
Most of the disruptions will take place during the weekends, the MBTA said in a press release.
The agency said the decline in service outages reflects its progress made on system improvements over the past several years. The MBTA reported 132 days of shutdowns in 2026, down from 190 in 2025 and 274 in 2024.
“Rebuilding tracks, modernizing signals, upgrading accessibility, prioritizing safety — these bold, accelerated investments in the system are how we deliver improvements and a system riders can be proud of today and into the future,” MBTA General Manager and CEO Phillip Eng said.
In 2027, the MTBA said it plans to complete major signal upgrades on the Red and Orange Lines and finish signal improvements on the Green Line’s central tunnel ahead of new trains. The agency will also continue track maintenance across subway lines and upgrade radio communications throughout the system.
Other planned projects include station accessibility improvements, bridge repairs, and infrastructure maintenance, the MBTA said.
Here is a breakdown of the anticipated service disruptions in 2027. The MBTA said dates could change depending on weather and construction needs. The agency said it will provide advance notice of service interruptions and information about alternative travel options.
Green Line
- Symphony Station: remains closed through spring 2029 for accessibility improvements, including four new elevators
- North Station, Babcock Street, Kenmore, and Heath Street: Crews will complete signal upgrades and inspect the central tunnel.
- Jan. 9-10
- Jan. 16-24
- Feb. 6-7
- Feb. 20-21
- Feb. 27-28
- Sept. 18-19
- Sept. 25-26
- Reservoir to Riverside: The MBTA will repair the Hammond Street Bridge in Newton, passing over Green Line D Branch tracks.
- Aug. 21-22
- Aug. 27-30
- Government Center to East Somerville and Union Square: Crews will replace the rail throughout the entire shutdown area, including other track work in some sections.
- Nov. 13-21
- The suspension will extend to Medford/Tufts Nov. 13-14 for removal of the Broadway Utility Bridge.
- Babcock Street to Boston College: The MBTa will raise platforms eight inches above the top of the rail and upgrade platforms for improved navigation.
- Dec. 4-5
- Dec. 11-12
- Dec. 18-19
Red Line
- Alewife to Kendall/MIT: Crews will inspect the underground Red Line tunnel.
- Jan. 30-31
- JFK/UMass to Quincy Center: Crews will carry out pre-commissioning work required before final testing and deployment of the upgraded signal system.
- April 8-12
- Broadway to North Quincy (Braintree Branch) and Broadway to JFK/UMass (Ashmont Branch): The agency will continue signal upgrades and replace tracks and switches.
- April 24-25
- Kendall/MIT to JFK/UMass: Crews will install radio equipment and inspect the underground tunnel.
- July 17-18
- July 24-25
- JFK/UMass to Braintree: Crews will replace tracks and repair the Furnace Brook Parkway Bridge.
- Aug. 7-15
- Quincy Adams to Braintree: Trains will operate on a single track while crews complete signal upgrades and testing.
- March 26-28
- April 2-4
- April 9-11
- April 23-25
- Alewife to Harvard: Trains will operate on a single track for radio upgrades.
- Nov. 6-7
- Nov. 13-14
Orange Line
- Back Bay to Forest Hills: Crews will inspect tunnels and make improvements at Ruggles Station.
- March 6-7
- North Station to Ruggles: The MBTA will replace tracks throughout the affected areas.
- May 15-23
- North Station to Back Bay: The agency plans to install radio equipment in July. In October, crews will advance construction of two accessible transfer elevators at Downtown Crossing.
- July 10-11
- Oct. 8-11
Mattapan Line
- Ashmont to Mattapan: Crews will perform track maintenance and upgrades.
- March 27-28
- April 3-4
Blue Line
- Bowdoin to Airport: Crews will replace tracks throughout affected areas in June. The MBTA will install radio equipment in the tunnels in October.
- June 18-27
- Oct. 23-24
Commuter Rail
Needham Line: The agency plans to replace track ties between Forest Hills and Needham Heights.
- March 1-5
- March 8-12
- March 15-19
- March 22-26
- March 29-April 2
- April 5-9
- April 12-16
- April 20-23
- April 26-30
- May 3-7
- May 10-14
- May 17-21
Newburyport / Rockport Line: Crews will work on track ties, with weekday disruptions between Newburyport and Ipswich.
- March 8-12
- March 15-19
- March 22-26
- March 29-April 2
- April 5-9
- April 12-16
- April 20-23
- April 26-30
- May 3-7
- May 10-14
- May 17-21
- May 24-28
- June 1-4
- June 7-11
- June 14-17
- June 21-25
- June 28-30
South Station: The MBTA will continue work on the South Station Tower One project, suspending service between certain stops.
- South Station to Braintree: March 20-21; April 3-4
- Back Bay to Forest Hills: March 20-21; April 3-4
- Foxboro to Walpole: March 19, March 22, April 2, April 5
Worcester Line: Crew will upgrade tracks at Newtonville, suspending service between Back Bay and Framingham.
- June 5-6
- June 26-27
Needham, Worcester, Providence/Stoughton, Franklin/Foxboro Line: Crews will work on South Station’s Cove Interlocking rail junction.
- June 18-20
- July 30-Aug. 1
- Aug. 27-29
- Sept. 17-19
- Oct. 22-24
Lowell Line: The agency plans to remove the Broadway Utility Bridge.
- Nov. 13-14