Ashland’s Kreher Park to be redeveloped
By Ashland Daily Press,
2025-04-22The bathhouse at Kreher Park in Ashland is set to be replaced as part of a redevelopment project.
Work is scheduled to start May 1 and expected to take six months. Crew members from Huffcut Concrete of Chippewa Falls and Dreamland Contracting of Cable construct the project.
Plans call for concrete foundation work at the bathhouse, installation of water and sewer lines and a precast building that will become the bathhouse. Elsewhere at the park, new campsites will be constructed.
City officials hope the building will be replaced by the third week of June to ensure the new bathhouse is open for the July 4 holiday. The park is expected to open as usual in mid-May to recreational vehicles.
The project is supported by a Department of Natural Resources Stewardship Grant and American Rescue Plan Act funding.